VME Process selected by Siemens Energy to provide a Fuel Gas Treatment Package for the Mero 3 FPSO (Marechal Duque de Caxias) in Mero field offshore Brazil.

MISC Berhad (Malaysian FPSO operator) awarded Siemens Energy an EPC contract for eight complete topsides modules for the FPSO.

The Mero field is an ultra-deepwater oilfield situated approximately 180km offshore of Rio de Janeiro, Brazil. FPSO Mero 3 is a spread moored Floating Production Storage and Offloading unit (FPSO). The FPSO, with the capacity to produce 180,000 bpd of oil and process 12 million Sm3/day of gas, will be installed in an in-water depth of about 2070 meters. Production is expected to start in 2024.

From https://www.offshore-mag.com/

Project background:

  • Award date: 18-Jan-2021
  • Project duration: 12 months (Feb-2022)
  • Project management team: VME Technical Services, Malaysia
  • Skid fabrication: PTVME, Indonesia

VME’s scope of work and supply for the FG Skid:

  • Process design, guarantee, fabrication, inspection and testing, DNV certification and supply of equipment
  • 1 x 100% Fuel Gas Scrubber
  • 2 x 100% Fuel Gas Coalescers
  • 1 x 100% Fuel Gas Superheater
  • Skid size: 8.5m L x 5.5m W x 11m H
  • Skid weight: ~140T
  • The package will supply superheated fuel gas to the GTGs, GTCs and other users
  • The skid will be located on Topsides Gas Dehydration & DCPU Module S20
Comments are closed.

We're on your side.

Step one: Contact VME

Call: (903) 561-4082
Email: [email protected]
OR fill out the form on this page

Step two: Confirm we’re the right fit for you

Within 1-2 business days, we’ll connect you  with an expert who will learn everything we need to know about your project so you have an accurate quote, projected timeline, and reliable expectations.

Step three: Achieve your goals

We’ll fight for you and your success every step of the way.